Change Control Procedure

Rahul Kashyap
0
Change Control Procedure
Purpose
To describe the Change Control Procedure for systematic documentation of all changes that is done in the process, procedures, materials, equipment’s, systems and to review each change for its impact on process/ procedures &quality/ safety/ identity of the product due to the change.

Procedure
Preamble:
Change control system ensures continual improvement is undertaken in a timely and effective manner.  It should provide a high degree of assurance that there are no unintended consequences of the change.
Definition
Change Control
It is a control system for documenting, evaluating, approving and implementing changes that describes the action taken when a change is done that may affect product quality or reproducibility of the process. This ensures that sufficient supporting data are generated to demonstrate that the changes results in a product or process of the desired quality, consistent with the approved specifications and regulatory requirements.
Minor Change
The change, which are unlikely to have any detectable impact on the formulation, identity, quality, safety, efficacy, purity and establish system and procedure.
Moderate Change
The changes, which are likely to have a significant impact on the formulation, identity, quality, safety, efficacy, purity and establish system and procedure.
Major Change
The changes, which have significant impact on the formulation, identity, quality, safety, efficacy, purity and establish system and procedure.
Initiation of Change Control
Originating department shall send request for the change control to QA.
Executive/Designee-QAD issue ‘Change Control Form’ with stamping “CONTROLLED COPY Issued by” along with signature and date in red ink on top right corner on first page of change control format, second page onwards “CONTROLLED COPY” stamp in red ink on top right corner on all pages.
Executive/Designee- QAD assigns an alphanumeric number to change control
If any separate change control log required to be maintained as per customer requirement change control numbering shall be done with suffix as first letter of customer Company name.
The change proposal shall be logged by Executive/Designee QAD in “Change Control Logbook “.
Originator select the change required in, from the options provided in change control form and provide the brief details of existing and description of proposed change along with reason / rational / justification for change. Originator shall also attach documents, in support of justification provided for the proposed change if necessary.
Head of Originating department review the change proposal, identify the impacted system, process and documents due to change proposal, but not limited to, “Guidance for selection of actions consequent to changes” and shall record the same in change control Form.
A project plan shall be prepared by Head of originating department in consultation with other department heads for changes related to long time period changes such as modification of facility, procurement of major equipment/ Instruments and introduction of new software. The project plan contains the details of project, deliverables, time frame associated with tasks, responsibility and milestones. The project management plan shall be prepared “Project Management Plan”.
Handling of Change Proposal
The proposals for change initiated shall be handled through ‘Change Control Form’.
The supporting documents, that provide details of review, approval and implementation of the proposal, from other departments or Customer and shall be enclosed to the change control form.
For handling the change control, follow the procedure described in “Change Control Flow Chart.
Review by other Departments
The QA shall select the other departments and other corporate functions based on the guidance given in “Matrix for notification of changes to individual department” and identify the names of the selected functions by indicating with a tick mark in the applicable box in change control form.
Executive/Designee- QAD forward the Change control with supporting documents to Head- QA for review and approval.
Classification of Change:
Based on evaluation of the change proposal and review comments the Executive/Designee-QA shall classify the change as minor, moderate or major (current version) “Change Control Initiation and Type of Typical Changes” and provide reason for classification.
Quality Assurance review and approval of Change Control
QA shall review the change proposal, impact assessment to change proposal, supporting documents and classification of change.
After review Head/Designee-QAD shall finalize action to be taken as per the impact assessment form.
Based on the comments from the other departments and as per the impact assessment, Head/Designee-QAD shall provide the decision on Change Control proposal “APPROVED/REJECTED” .
On receipt of approved/rejected Change Control from Head/Designee-QAD, QA person shall intimate to concerned department.
Current regulatory requirements shall be considered during assessment of change proposal (where applicable). If the change requires notification to customer / relevant regulatory authorities, it shall be notified to them through QA / Regulatory department and approval shall be obtained before implementation.
Approval / Rejection of Change Control by Customer/ Regulatory Agency
Head/Designee-QAD shall forward the change control proposal for approval or rejection to Customer or Regulatory Agency (need based mail confirmation can be obtained) e.g.  for Filing of variation, notification for corrective action if any etc.
Need  based  scanned  copy  of actual  change control proposal can be shared with  customer  for  their reference, if requested.
On receipt of change control from Customer or Regulatory Agency, Head/Designee-QAD shall verify the comments of Customer /Regulatory Agency and approval / rejection of change control proposal.
On the basis of the comments by Customer or Regulatory Agency, Head/Designee-QAD shall forward the same along with documents to concerned department for further implementation.
In case of rejection of change control proposal from Customer or Regulatory Agency, change control shall be considered as rejected even after approval of QA and same shall be intimated to concerned department by QA.
Implementation of Change Control Proposal
The change control initiated shall be implemented by Head of the originating department under the supervision of Head/Designee-QAD.
After completion of the identified activities, the status shall be updated by entering the completion date for each activity in the form “Change Control Form”.
Originating department Head along with QA shall be responsible for on time initiation, implementation and closing of change controls.
After implementation of any change, an evaluation shall be undertaken to confirm the quality objectives are achieved and that there is no unintended deleterious impact on product quality.
An uncontrolled copy of duly signed first page or the summary page of the documents shall be enclosed to the change control form to confirm the completion of activities. List of enclosure shall be documented in the closure section of the change control.
Post Implementation of Change Control
After implementation status verification, Head/Designee-QAD shall decide on, if Post Implementation impact assessment is required or not required for the change control proposal.
If post Implementation impact assessment is not required, Head/Designee-QAD shall document the decision as not required in change control form and reason for not requiring the assessment should be documented.
If the change control requires post implementation impact assessment, Head/Designee- QAD shall decide  on the number of days and/or number of batches which need to be monitored (as applicable),  after which Post Implementation impact assessment need to be carried out.
Rationale for selecting the number of batches and/or time period shall be documented in the change control form.
The final closure of change control shall be done after completion of post implementation impact assessment.
Closure of Change Control
All the change proposals shall be approved or rejected within 30 working days from the date of initiation of the proposed change control.
Once the Change control is approved, implement the proposed change for minor and moderate within 90 working days. In case of change control for establishment of major equipment, instrument, software/hardware systems, facility expansion / modification, new API vendor etc., change proposal shall be implemented within one year.
Executive/Designee-QAD verifies the current implementation status of the proposed change control during closer verification and identifies the closed and open point of implementation plan.
Extension of Change Control (If Not Closed Within timeframe)
However, if change control is not closed within specified time period, Head of originating department shall make request as per respective format of Format/Logbook Issuance Request Form for “Extension of Time Period for Close out of Change Control”,.
Head of concerned department shall fill the justification for open implementation plan, required extension period with requested targeted date of change control closer and shall forward to Quality Assurance department.
Based on the Request for “Extension of Time Period for Close out of Change Control” Executive/Designee-QAD will review the change control.
Extended period for closing of Change Control is of 30 working days for minor, moderate and major Change Control. Only three extensions shall be allowed for closing of Change Control.
In case, originating department not able to complete the change proposal / identified activities / review of effectiveness of implemented change control (if applicable) within the extended target completion date, a CAPA shall be initiated by following the procedure of “CAPA”.